2/9/26 Update::
- The full intersection at Morris/Shelby Street will be closed through February (left turns are currently allowed, but that will be changing) while Citizens Energy work continues. In March they’ll be moving into the intersection @ Prospect
- Information about impacts to IndyGo’s Red Line (bus route 90) can be found here. The Red Line currently does not pick up on Virginia & Woodlawn, Shelby & Pleasant Run, or Shelby & Raymond. IndyGo Route 26 does still pickup at Virginia & Woodlawn
- The initial plans for construction allowed for southbound traffic to use the “Local Route” detour to access Shelby St near the underpass. There was a misunderstanding by workers when construction started, and equipment was placed to block this path. As of this week, that path should be opened.
- Also with this update, Cottage Avenue will be accessible from Shelby St again.
2/2/26 Update:: Due to the snowstorm last weekend and the frigid temperatures this past week, work did not progress as planned. One of the changes mentioned last week will now be happening this week:
- Shelby and Morris streets to be completely closed for 3-4 weeks
There will be a “Soft Closure” of Morris where it meets the I65 Exit…where residents & those heading to the Shelby St. businesses will be able to go around the baricade. Other traffic is encouraged to take Leonard St. around the closure.
Morris St. will then be closed on both sides of Shelby St. This means that where you could previously turn down Shelby St. by the Fountains to access Morris St. behind the Fountain Square Theater Building, you’ll have to use Prospect St. to Linden St. as an alternative.
1/26/26 Update:: 2 big changes this week, closures expected to begin sometime the week of Jan. 26 (exact date depends the weather)
- Shelby and Morris streets to be completely closed for approximately three weeks
- Shelby Street will temporarily reopen at Orange Street
1/19/26 Update:: CEG Water currently plans to close the intersection of Shelby and Morris streets on or after Monday, Jan. 26. More information will be provided as it becomes available.
1/12/26 Update:: Shelby Street between Cottage Avenue and Morris Street will likely be closed through July. All merchants in these blocks are remaining open, and need your support! It’ll be more difficult to get there, but totally worth it!
On the West side of Shelby: On the Rocks, Goodwill, Fountain Square Brewery, Elf ‘n Moon, Cavity Factory, & Black House Cafe.
- Detour: West on Prospect, to St. Patrick, to Morris, to Parking Lot/through street behind Forte
- Parking: Behind Forte (Parking Lot for old Dollar Store & IMPD SE District), Goodwill Parking Lot, FS Brewery, & Old Longshot Lot
On the East side of Shelby: Magdalena, West Fork Social House, Brass Ring Lounge, Super Tortas, Nine Lives Cafe & Cat Lounge, DIDFit, Bow Wow Meow Boutique, Artesanal Pasteleria Panaderia, Hello Hair Studio, The Salvation Army, & Macha Eye Care
- Detour: East on Prospect or Morris to residential streets (Olive/Linden/Laurel)
- Parking: Mostly residential, a few merchants have some small lots on their own
Additional parking:
If you don’t mind a few minutes walk; Free Lot on Woodlawn across from Flipside, paid parking on Morris behind the Murphy Arts Center
1/5/26 Update:: Construction will resume today after 2 weeks off for the Holidays.
12/22/25 Update:: Construction will be paused for the next 2 weeks for the Holidays. Crews will return to the area on Monday, January 5 to continue installing new infrastructure at the intersection of Cottage Avenue and Olive Street. Closures will remain in place.
12/15/25 Update:: Work for this project has officially reached Shelby Street. Citizens Energy Group has begun replacing the water mains along Shelby and services lines to the merchants and residents. This portion is part of Phase 3 of the project, which starts near Cottage & Shelby, and should take approximately 3 months as Citizens works North towards Morris. Residents and Merchants along Shelby should keep an eye out for notifications from Citizens regarding temporary water shut offs that will be necessary to complete these replacements. Citizens has committed to 24 hours notice, but we’ve pushed them to increase this as much as possible.
As Citizens finishes their work in sections, DPW will come in behind them to start on the drainage and structural changes along Shelby. That portion is expected to take until June/July (pending any weather delays).
We’ll continue working with all parties involved to ensure there’s plenty of signage for detours, closures, and businesses. We’ll also address any concerns that are brought to us.
July 11, 2025:: AES Utility Pole Maintenance
12/1/2025:: Citizens Energy Water Main Replacements Begin