Fountain Fletcher District Association

   

Learn more about the latest road work and construction for the Fountain Square Drainage Project.  We’ll make every effort to update it promptly. Be prepared for unexpected changes. Leave early and plan ahead.  All Fountain Square businesses are open during construction. Plenty of free parking can be found throughout the neighborhood and on Virgina Ave.

Please direct questions or comments about the project to the FSdrainage@gmail.com or (317) 981-2515. They will respond to you as quickly as possible.  You can subscribe here to receive their weekly updates (every Friday.)

Project Updates

10/17 Update:  All Fountain Square Roads Are Open
As crews work toward substantial completion of the project, all streets are now open. Work in the area may require temporary lane restrictions while crews work on punch list items, pavement markings, and touch up work on inlets/manholes. Flaggers will be on site during that time.  Work continues on the Shelby Street bridge over Pleasant Run. The project remains on schedule for reopening later this construction season. The pedestrian bridge and trail west of the project remain open throughout construction.


8/21/26 Update
: As we near the half way point, there has been a wealth of progress made with several sections of roads preparing to reopen.

  • Woodlawn Excavation: On Monday, August 24, Woodlawn will be restricted to local traffic only between Virginia Avenue and Shelby Street. Weather permitting, flaggers will be on site while crews excavate Woodlawn and begin reconstruction. During this restriction, traffic on Virginia Avenue will be able to turn east or west on Prospect Street. Woodlawn will reopen and turns from southbound Virginia to eastbound Prospect will be prohibited by the middle of next week.
  • Cottage and Olive Nearing Completion: Crews have completed paving and concrete restoration on both Cottage Avenue and Olive Street. There may be some brief clean-up work in the area this fall, but both streets will remain open.
  • Shelby Street Section Now Open: Shelby Street is open to traffic between Sanders Street and Pleasant Run Parkway North Drive. However, there is still no parking allowed on Shelby Street within the project limits.
  • Paving Begins North of Morris: Crews have begun paving on Shelby Street through the Morris Street intersection and moving north toward the fountain. The intersection closures for Shelby Street at Morris and Prospect remain in place. Prospect Street is closed at the Virginia/Shelby intersection, and you cannot access Shelby Street from Prospect.
  • INDOT Closure Of Morris Street / I-65 Bridge: As part of its I-65 Safety and Efficiency Project, INDOT has closed the Morris Street bridge over I-65. Eastbound Morris Street is closed between the southbound I-65 on-ramp and northbound I-65 off-ramp for bridge rehabilitation until early September. You can learn more at Home – I-65 Safety & Efficiency
  • Shelby Street Pleasant Run Bridge Update: Now that river levels are decreasing, work will continue on the Shelby Street bridge over Pleasant Run. Crews have begun placing false work and forms as they prepare to pour concrete sidewalks and repair the arch. The project remains on schedule to reopen later this year. Indy DPW appreciates the community’s continued patience, support, and understanding as these critical improvements move forward.
  • Utility Relocation Update: AT&T Distribution has completed their work between Morris and Shelby streets. The intersections of Shelby Street at and between Morris and Prospect will remain closed while the contractor paves and reconstructs the roadway. AT&T will be installing conduits going north on Virginia, which will require parking restrictions along the west side of Virginia. After that, crews will work in the alley on Shelby Street between Prospect and Woodlawn.

5/18/26 Update:

  • BIG Updates this week! Prospect and Morris Streets are closing again! This is the first time that both areas will be closed at the same time.
  • Please see our map for visuals of the closures and detour routes
  • Weather permitting, DPW crews plan to open Shelby Street to two-way traffic from Pleasant Run Parkway North Drive all the way to N. Orange Street early next week. This is dependent on dry weather to complete the pavement replacement on Shelby Street

5/10/26 Update:

  • No major updates this week. Coming May 15th; Prospect will be closed again, blocking through traffic coming down Virginia Ave.

4/13/26 Update:

  • No major updates this week. Work continues

4/6/26 Update:

  • Citizens has finished up their portion of this project! This means that there shouldn’t be any more water outages. AT&T will be starting the next phase of their work this week, and hope to wrap up in a few weeks.
  • Through April 12th; Shelby Street will be open between Orange St. and Sanders St.
  • On/after April 7th; The intersection of Virginia/Prospect/Shelby will be closed again. Parking in this section is still allowed, but use Woodlawn to get to Prospect.
  • Be aware that Woodlawn is a narrow, neighborhood Street. Be patient, and considerate
  • Various neighbors & merchants will be using this area on Virginia Ave. for events. Keep an eye on social media and come join us!
  • From April 7-11th; Morris & Prospect at I65 will have overnight closures for INDOT’s bridge work.
  • Beginning April 13th; Pleasant Run Parkway North Drive will open and Pleasant Run Parkway South Drive will close
  • This isn’t related to the Drainage Project, but it does affect travel through and into the District.
  • On/after April 13; DPW is closing the bridge on Shelby Street, over Pleasant Run Creek (between Pleasant Run Parkway North and Pleasant Run Parkway South). This closure will last through October. This update will be added to our Closure Map.

3/30/26 Update:

  • Virginia & Prospect Ave.’s will temporarily re-opened this week & weekend. This is scheduled to close again on April 7th.
  • Shelby St. between Prospect & Woodlawn will be closing this week to allow Citizens work to continue. This will also close the intersection of Shelby and Woodlawn. This work is expected to take between 1 and 2 weeks
  • INDOT is also planning work that affects the District. Morris and Prospect streets will experience overnight closures for approximately eight business days to set structural steel on the new NB I-65 bridge. Weather permitting, this will occur between March 30 and April 2, and again from about April 7 to 11. These closures will occur between 8 p.m. and 6 a.m. each night.

3/23/26 Update:

  • No major updates this week.
  • Morris Street will remain open this week for traffic crossing Shelby Street from west to east
  • Crews will soon start pouring sidewalks and curbs for the new rain gardens on the South end of Shelby

3/16/26 Update:

  • No major changes to the Drainage Project this week. However, INDOT projects will be affecting the neighborhood:
  • Expect nightly closures to Morris and Prospect, west of Fountain Square in Bates Hendricks. Closures will commence as INDOT works on their I-65 Safety and Efficiency project.
  • INDOT will also be closing the I-65 On Ramp on Calvary St (between FS & FP) starting on or after today. This closure will remain until this Fall. We requested a detour route map for this closure but have not been provided one yet.

3/9/26 Update: Major Change Starting Today

  • Citizens plans to begin the next Phase of their work on or after Monday, March 9. This Phase will CLOSE the intersection of Shelby/Prospect/Virginia, while work is done in the intersection and Westbound on Prospect.
  • Traffic will have access to parking along Virginia Ave in front of The HI-FI, Square Cat, and the other merchants on this block.
  • Traffic will not flow through this intersection. Travelers needing to go around this area will need to use Woodlawn.
  • Local/Light traffic coming West on Prospect into the Square will ONLY be able to turn right on Shelby St. after Olive St. (or park along Prospect)
  • IndyGo routes for the Red Line and Bus Line 26 won’t pick up at the Virginia/Woodlawn Bus Stop
  • Fletcher Place and Prospect bus stops will stay open
  • New temporary stops will be set up along Calvary and English Ave. for Route 26 (see map below)
  • The Red Line will continue to bypass Fountain Square, and pick up in Fletcher Place and on Raymond

3/2/26 Update:

  • Please slow down through the neighborhood and the construction! We know detours can be annoying, and that the routes around construction change often, but pedestrians & workers have noticed an increase in dangerous driving. Getting to your destination 60 seconds earlier isn’t more important that your neighbor’s safety!

Major Change Coming March 9!!

  • Citizens plans to begin the next Phase of their work on or after Monday, March 9. This Phase will CLOSE the intersection of Shelby/Prospect/Virginia, while work is done in the intersection and Westbound on Prospect.
  • Traffic will have access to parking along Virginia Ave in front of The Hi-Fi, Square Cat, and the other merchants on this block.
  • Traffic will not flow through this intersection. Travelers needing to go around this area will need to use Woodlawn.
  • ALocal/Light traffic coming West down Prospect into the Square will ONLY be able to turn right on Shelby St. after Olive St. (or park along Prospect)
  • We’re still awaiting for IndyGo to confirm bus route changes


The following information has been collected from public presentations and online information. As we continue to receive more information, we’ll do our best to update everyone via e-mail and this page. If you have questions or concerns, please don’t hesitate to reach out to us (info@fountainfletcher.com) and we’ll do our best to find an answer for you, or direct you to someone who can help.

City Project Number: SD-32-014

Project Description: The Fountain Square Area Drainage Improvements Project will help relieve flooding, primarily along Shelby Street from Woodlawn Avenue to the north and along Cottage Avenue and Olive Street to the south. Surrounding streets in the Fountain Square neighborhood will also benefit from the construction of the new separate storm system, from both the initial and planned future phases of the project.

Stormwater on Shelby Street will drain to the bioretention system (aka: rain garden), improving water quality and quantity management in the area. The rain garden feature will also improve safety along the cycle track in this area.

One block of Woodlawn Avenue will also be repaved between Virginia Avenue and Leonard Street.

Project Timeline (subject to change):

These slides were provided by the City of Indianapolis and Indianapolis Department of Public Works, and are publicly available HERE.